We have had a terrible time with the weather on the new spare hole, the shapers arrived on April 2nd only to get one days work completed before the heavens opened up and with our heavy clay soil they were unable to work for the remainder of that week. We were able to get back on the site the following Monday only to be rained out again until Wednesday afternoon, and with a few more days of rain the shapers have returned to Melbourne to allow us to get all the drainage and new irrigation in before they get back in town to finish of the hole. Out of a possible 14 days work we have only been able to get on site 6 days which has pushed our finish date out a week or so, we originally wanted the turf down by Anzac day however we wont be able to reach that target
Here are some pictures of the works so far:
Gravel getting installed on the greens sub-base
Heavy rain on Tuesday 16th April putting halt to proceedings
Bunker 40m short of the green roughly shaped up
Greenside bunker roughly shaped up
I will keep posting some more photos as we keep progressing with the new hole
Regards
Ryan
